Upgraded Slag Project (UGS)
Custom design of an innovative slag processing route. Greenfield process plant on an operating site.
Scope of Services:
- Process development followed by full EPCM, including:
- Process evaluation and pilot plant testwork
- Basic engineering
- Custom design of thermal treatment process equipment
- Process and equipment design & detailed engineering
- Full construction and project management including
- Contract supervision and quality assurance
- Contract administration
- Safety and labour relations
- Planning and scheduling
- Estimating, capital cost control and engineering control
- Procurement, expediting and inspections
- Commissioning of facilities and all systems
- Plant start-up
Project Highlights:
- Duration ~ 26 months from start of basic engineering to startup
- 18 months for construction
- EPCM peaked at 220 professionals
- Construction trades peaked at 1100 people
- Achieved one of the best Canadian safety records in the industry
- Global procurement
Project Cost: Cdn$426 million
Client: QIT-Fer et Titane Inc.
Location:Québec, Canada
Start:1995
Completion:1998
|