HATCH
   
corner image
项目经验
Hail Creek
Hail Creek 选矿厂,澳大利亚
Melt Shop & Caster Complex
熔炼车间和浇铸机组,加拿大,魁北克
Million Tonne Expansion
百万吨扩建工程,南非
Upgraded Slag Project
升级矿渣处理项目,加拿大,魁北克
Mine Upgrade Project
矿山升级项目,2000年,南非
更多...

工业矿产

项目
专业论文

Mining Plant 'E'Mine Upgrade Project2000 (MUP 2000)

Increase of RBM dredge mining capacity with a new Mining Plant ‘E’, and upgrade of existing Mining Plant ‘A’, including all associated infrastructure requirements.  The objective of the project was to maintain RBM Slag production through the Smelter beyond the year 2000, and thus extend the life of mine.

Scope of Services:

  • Conceptual studies, including testwork, development of PFD’s and cost estimates for options
  • Process development followed by full EPCM, including process evaluation and pilot plant testwork; basic engineering; process and equipment design and detailed engineering
  • Full construction and project management including contract supervision and quality assurance; contract administration; safety and labour relations; planning and scheduling; estimating, capital cost control and engineering control; procurement, expediting and inspections; commissioning of facilities and systems

Project Highlights:

  • Duration was 40 months from conceptual studies to start-up
  • 3.5 million fatality-free manhours worked with an LTIFR of 2,0
  • EPCM peaked at 100 professionals, with an integrated Hatch/RBM team
  • Construction trades peaked at 1500 people
  • Extremely rapid commissioning ramp-up
  • Mining Plant ‘E’ produces some 40% of total RBM production, and is the largest floating concentrating plant in the world
  • Plant metallurgical and production throughput performance has exceeded the design specifications

Project Cost: R861 million

Client:Richards Bay Minerals

Location:Richards Bay, South Africa

Start:1996

Completion:1999

Copyright © 2010 Hatch Ltd. | privacy statement | contact webmaster